Case Study #4

Morrisons Case Study

What they needed

MSC were contacted by a contractor to Prince Build Ltd who is the principal contractors to Morrison’s Supermarkets to help a critical situation. The concrete slab that had been laid had cured too quickly and had become very uneven as a consequence. The project time scale didn’t allow for it to be excavated and re-laid in time.

What we did

MSC were able to diamond grind the surface to get it level and then pump a Webber Industrial Screed over the whole area varying from 5mm to 15mm thick to get a super-level finish. This could then be put into operation the following day putting the whole project back on track.

Client Feedback

The job was completed in time and within budget to a satisfactory standard. Clearly everyone was thrilled with the job and MSC can expect more work from these important clients in the future.