Case Study #23

West Yorks Joint Case Study

What they needed

After 20 years of wear and tear the floor areas in the warehouse and archives department of a Yorkshire Government establishment were in desperate need of attention. There were holes and cracks and the surface was creating a lot of dust up.

 

Corridor before picture for West York's Joint

What we did

Maintenance Supplies Contracts vacuum shot blasted the floor and exposed all the holes and cracks. These were repaired with an epoxy mortar, Res-Fix. After this some areas had two coats of high build epoxy resin Grip-Seal HB on them and other areas had the thicker 2mm to 3mm self levelling epoxy screed, Grip-Seal SL. This as a project of several hundred square meters in tight thin aisle ways as well as open areas.

 

Corridor after picture for West York's Joint

Client Feedback

The job was completed in time and within budget to a satisfactory standard. The client is delighted with another successful job.

Warehouse after picture for West York's Joint