One of B&M’s busy distribution centres needed new floor markings, including walkways and inspection put borders. This was needed in order to fit health and safety requirements and because of the work carried out, there was no way for the centre to be closed.
Our team spent a couple of weekends installing the new flooring, working around staff to create minimal disruption to the running of the business.
We began by grinding and blasting the floor to get a key, then installed a super-fast drying MMA resin, to ensure full access could resume as soon as possible.
This type of resin sets within just 30 minutes which allowed the centre to maintain their around the clock operations.
Our client at B&M Bargains were very appreciative of the speed with which our team completed the project with minimal disturbance and the standard of the work carried out.