What they needed

The floor at Bendalow Vets, Swinton, Manchester had deteriorated and presented a health and safety issue. The access was difficult as the only day the practice was shut is on a Sunday. Much of the equipment was too heavy to move.

What we did

MSC stripped the floor tiles with a heavy duty tile remover and then diamond ground the concrete to get down to a clean surface. A multi-layered MMA Resin and flake system was installed. Each resin layer cured in 40 minutes enabling the 6 rooms to be all completed within one day. The vets opened as usual on the Monday morning.

Client Feedback

The job was completed in time and within budget to a satisfactory standard.