Case Study #8

DHL Case Study

What they needed

The floor area inside the loading dock was hazardous due to water being brought into the building and being a slip hazard for fork lift trucks. The other problem is that this area was a 24/7 area and it was difficult to set it aside for repair work for longer than 5 hours.

What we did

Maintenance Supplies Contracts were able to diamond grind the floor surface with vacuum extracted grinders to avoid any dust in the air. They then applied two layers of MMA Fast curing resin with an anti-slip aggregate in between. This system was so fast in curing that the area of floor was back in service within 5 hours and the encapsulated aggregate and resin system was a cleanable surface.

Client Feedback

The job was completed in time and within budget to a satisfactory standard.